The HWY 2 over the CN Railway Bridge Rehabilitation project (BF76060E) involved a comprehensive rehabilitation of the existing bridge structure, including the removal and replacement of various components, such as the high-density concrete overlay, curbs, bridge rails, and deck joints. This complex project required meticulous planning, coordination, and execution to ensure the structural integrity and safety of the bridge.
Our Commitment:
At ERK Construction Inc., we are Committed to Sustainability and Environmental Responsibility. We strive to minimize our environmental footprint and promote sustainable practices in all our projects, while delivering high-quality infrastructure solutions that meet the needs of our clients and communities.
Project Details:
- Project: BF76060E – HWY 2 over the CN Railway Bridge Rehabilitation, in Peace River, Alberta
- Client: Eiffage Canada Inc.

- Description: Remove and dispose of high-density concrete overlay on deck, remove existing curbs and bridge rails, remove existing deck joints and existing asphalt on approach slabs. Replace shear blocks between girders at both abutments, repairs to girders and concrete diaphragms. Jacking of bridge superstructure and resetting existing bearings/apply zinc coating. Construct new deck overhangs and curbs, supply and install new strip seal deck joints and seals. Supply and install new bridge rails and pedestrian safety railings, steel guardrails, deck waterproofing and asphalt paving on bridge deck and roadway approaches. Construct new concrete drain troughs, concrete slope protection repairs.
Our Role:
ERK Construction Inc. was the main subcontractor on this project, responsible for performing work as required by the client. Our scope of work included:
- Supplying carpenters, concrete finishers, ironworkers, and skilled laborers
- Concrete demolition and removals
- Deck joint, bridge rail, and utility removals
- Placing, finishing, and wet cure of concrete in all elements
- Formwork installation, removal, and performing concrete dry finishing for all elements
- Installation of embedded anchors in curbs
- Concrete repairs to existing bridge deck, surface preparations for waterproofing
- Application of finishes and sealers to curbs, deck overhang undersides, and abutments
- Site clean up, organizing materials, and other duties as required by the client
Key Statistics:
- Zero lost time injuries or incidents
- Adherence to the client’s strict international safety program
- Successful execution of the project despite challenging winter conditions and delays caused by a strike with CN Rail workers
Challenges Overcome:
- Northern Alberta climate and working in winter conditions
- Delays caused by a strike with CN Rail workers
- Working adjacent to a much larger project, restricting access
- Busy project site with multiple subcontractors on various work fronts being executed concurrently
- Ever-changing work front due to the nature of a large bridge rehabilitation project
- Client required craft personnel on other projects on short notice
Result:
The client and project owner were extremely satisfied with ERK Construction Inc.’s performance in the execution of the requested duties. By prioritizing sustainability and environmental responsibility, we aim to create infrastructure solutions that not only meet the needs of our clients but also contribute to a healthier and more sustainable environment for future generations.